Construction Progress

For those of you who don't have the privilege to drive by our construction site on a daily or weekly basis, below are a few photos of the construction progress. Check back for more updates, through to completion!

February 14, 2008

Building Completed.

September 19, 2007

Freshly painted and scaffolding is down.

August 29, 2007

Stucco Completion.

August 3, 2007

Wrapping the building for stucco.

July 10, 2007

Framing Completed.

June 7, 2007

Completing the Framing.

May 17, 2007

Framing the 3rd floor.

April 30, 2007

Second floor progress.

April 25, 2007

Starting the second floor.

April 4, 2007

Setting beams for the second floor.

March 8, 2007

Framing progress on the first floor.

February 28, 2007

Setting the steel posts and getting ready to frame the building.

Pre-Construction, 2006

Getting ready to start construction.